Sequential shift light array

Kit assembly


Install Resistors

  • R1,R2 Install included 100 ohm resistor (marked 101)



  • R3,R4,R5 Install included 270 ohm resistor (marked 271)



Install LEDs

Install LEDs so that the flat side on the LED case matches the outline on the board silkscreen.

  • Cluster A1,A2: Install green LEDs for L1 - L8
  • Cluster A3,A4: Install yellow LEDs for L9 - L16
  • Cluster A5: Install Red LEDs for L17 - L20


Wiring

Basic Operation

Wire pad +12v to ignition switched +12V.

To activate the following clusters:

  • Cluster 1: Connect A1 to ground
  • Cluster 2: Connect A2 to ground
  • Cluster 3: Connect A3 to ground
  • Cluster 4: Connect A4 to ground
  • Cluster 5: Connect A5 to ground

Integration with the Megajolt Lite Jr.

User outputs 1-4 + shift light output can be used to control the sequential shift light.

  • Cluster 1: Connect A1 to MJLJ User Output 1
  • Cluster 2: Connect A2 to MJLJ User Output 2
  • Cluster 3: Connect A3 to MJLJ User Output 3
  • Cluster 4: Connect A4 to MJLJ User Output 4
  • Cluster 5: Connect A5 to MJLJ Shift Light Output

Panel Drill Template

Use this image as a drill template if you wish to mount this behind a panel.


200 DPI template


Project Images




Shift light array assembled and illuminated